Note 6. Base current days ot supply (DOS) on a comparison of
the quantity of meals on-hand with the estimated meal
consumption rate. (The meal consumption rate should be based on
the population projected utilization factor, if this factor is
significantly less than 100 percent, i.e., approximately 80
percent or below. The utilization rate can be calculated by
dividing the average daily rations consumed by the average
daily population supported.)
Note 7. Base projected total DOS on a comparison of the total
quantity of meals on-hand through the next 5 days (to include
scheduled due-ins) with the estimated meal consumption rate.
(This rate should be adjusted by significant changes in the
projected population, as appropriate.)
Note 8. If DOS calculations are based on other than 100
percent meal utilization rate or other than B-C-B feeding
schedule, indicate this.
Note 9. Optional narrative provides commanders the opportunity
to advise USARCENT of problems, impact, and action(s) requested
of USARCENT, if any.