Subject: OPORD 64 90 FRAGO 4
Unit: VII CORPS
Parent Organization: ARCENT
Box ID: BX000218
Folder Title: 525-2B-8 PORT OPNS FORCE MODERNIZATION
Document Number: 6
Folder SEQ #: 158
HHC,Ist ID(F)
UNCLASSIFIED DHARRAN,SAUDI ARABIA
051200 FEB 91
OPORD 64-90 (FRAGO 4 to OPERATION DESERT DUTY)
TASK ORGANIZATION: See Annex A.
1. SITUATION.
a. Enemy Forces. No change from basic INSUM.
b. Friendly Forces. All Vil Corps priority vehicles have been or will
be painted given the current plan. In addition,several thousand other
vehicles, tracks and wheels, have been painted. The VII Corps continues
to deploy, with a number of vehicles deploying to the field without being
CARC painted.
2. MISSION. The 2d COSCOM CARC paints VII Corps vehicles in the TAA
effective 5 February 1991.
3. EXECUTION.
a. Commander's Intent:
(1) To CARC paint as many vehicle as possible in the TAA that
weren't painted in the ISA as a result of shortages of paint or
requirements to move to the TAA before being painted.
(2) To provide 2d COSCOM with technical experts and equipment to
establish, and complete painting VII Corps vehicles as paint supplies
allow.
b. Concept of the Operation.
(1) General. The 2d COSCOM assumes the mission of painting Vil
Corps vehicles in the TAA. The operation will be executed in four phases.
(2) Phase I (Equipment Transfer / Preparation for Movement). The
593d ASG and the Army Material Command (AMC) will sign the required
equipment over to 2d COSCOM on 5 February 1991 to establish two paint
lines. An additional two paint lines will be transferred to the 2d COSCOM
upon the completion of the paint operations in the Port of Da=an on or
around 8 February 1991.
(3) Phase II ( Establishing CARC Paint Site in the TAA). 2d
CARC paint site. AMC provides technical experts to
set up @nd supervise the paint site in the TAA, paint @ipment, paint,
and taping materials to prep vehicles. The 593d ASG provides the
maintenance tents to paint in. The 2d COSCOM p@ovides the personnel,
leadership, and limited equipment to run the site.
(4) Phase III (Paint Operations). The 2d COSCOM conducts CARC
paint operations in the TAA
(5) Phase IV ( Termination of Paint operations in the TAA). The
2d COSCOM is responsible for the disposal of the Maintenance Tents,
hazardous waste, and the transport of equipment back to AMC.
UNCLASSIFIED
DECLASSIFIED ON 13 Sep 1996 PER SECA Y (DAMH) UP SEC 3.4
EO 12958.
Document Page: First | Prev | Next | All | Image | This Release | Search
Document 2 f:/Week-25/BX000218/525-2B-8 PORT OPNS FORCE MODERNIZATION/opord 64 90 frago 4:092096155901102
Control Fields 17
File Room = jun96_declassified
File Cabinet = Week-25
Box ID = BX000218
Unit = VII CORPS
Parent Organization = ARCENT
Folder Title = 525-2B-8 PORT OPNS FORCE MODERNIZATION
Folder Seq # = 158
Subject = OPORD 64 90 FRAGO 4
Document Seq # = 102
Document Date =
Scan Date =
Queued for Declassification = 01-JAN-1980
Short Term Referral = 01-JAN-1980
Long Term Referral = 01-JAN-1980
Permanent Referral = 01-JAN-1980
Non-Health Related Document = 01-JAN-1980
Declassified = 20-SEP-1996