Document Page: First | Prev | Next | All | Image | This Release | Search
File: 980227_sep96_decls1_0004.txt
Box ID = BX005618
Folder Title = AFTER ACTION REPORT 403D MP PW CAMP
Unit = MISC
Parent Org = MISC
AFKB-AC-CA 2 April 1991
SUBJECT: After Action Report, 403rd MP PW Camp
h. Although the 403rd accepted EPW on 17 February, construction was
not completed. Gates, including sally parts, were a particular problem.
Material for the gates had to be scrounged and the unit lacked the
equipment needed to install the gates in the soft sand and hard sandstone.
The gates and sally ports eventually constructed were satisfactory +or
temporary use but would not have been acceptable over the long term. As
originally constructed each EPW camp consisted of 30 compounds spacially
organized into three enclosures of ten compounds each. However, the
compounds were not connected by barrier material. Even while housing EPW,
the 403rd continued to work on compound security. The exter4@ors of all
compounds in an enclosure were tied together with concertina. Sally ports
were constructed and concertina wire laid within the commons area of each
enclosure. Permanent lighting was not completed until 23 February 1991,
six days after we first began accepting EPW.
1. The goal of the 403rd was to have the camp operational before the
start of the ground war. This timeline was met. However, in order to meet
the timeliness resources of both the 403rd and all subordinat-- units had to
be dedicated to the construction of the camp. This included all vehicles,
material and personnel. The construction process took its toll on all
units involved and was accomplished at the expense of improvements in life
support areas for US personnel.
j. The end of the ground war was followed by a large influx of EPW.
The 403rd received 9,853 EPW in a seven day period beginning on 27
February. With this influx internal priorities shifted from construction
of the camp to life support for the EPW and inprocessing operations. The
rate at which EPW were arriving was too fast for inprocessing to keep up.
Compounds were challenged to get tents url fast enough to keep the EPW
covered at night and mess operations started to keep them fed. The initial
shortage of tentage was solved in early March. Food problems were solved
through the establishment of a supplemental mess to prepare food for the
compounds. The supplemental mess was initially set up by the 400th MP
Camp. EPWs were used as cooks and KPs. The supplemental mess was only
operational for about five or six days, but it was a critical five or six
days.
k. Sewage removal and water distribution remained problems. The water
problem was made more difficult to manage because of a decision by
supporting engineers not to construct roads around and through the
enclosures (a resource allocation decsion). Without a working water
system all water had to be delivered by truck. The soft sand made
traf-Ficability in parts of the camp impossible except for four wheel drive
vehicles. Much time was wasted and energy expended pulling two wheel drive
water vehicles out of soft sand. In retrospect the water problem could
have been most easily been solved with a complete TWIDS System to include
both the wholesale components, which were on site, and the retail
components which were-not rn site. The retail components include the two
inch hosing and fixtures needed to get water from the big line to the
compounds. The sewage lines needed to be buried and laid out with a 4%
downhill slope towards the lagoon.
4
Document Page: First | Prev | Next | All | Image | This Release | Search