Subject: DESERT SHIELD STORM AFTER ACTION REPORT PHASE 1                 

Unit: 1ST ID      

Parent Organization: VII  CORPS  

Box  ID: BX001045

Folder Title: AFTER ACTION REPORTS PHASE I MOBILIZATION AND DEPLOYMENT                                        

Document Number:      20013

Folder Seq  #:         16







                                        UNCLASSIFIED
                                                                         06/28/9'1
                                      JULLS LONG REPORT

            1. (U) JULLS NUMBER: 32S47-23845 (00224), submitted by RILEY
            PTM-C, MR WALTER, 856-2225, (913)239-2225.

            2. (U) Operation DESERT SHIELD conducted by USCENTCOM on 02/06/91.

            3. (U) KEYWORDST RWO (REAL WORLD OPS), USA (US ARMY), (3UARD
            COMPONENT, RESERVE COMPONENT, C2 (COMMAND AND CONTROL), COMMAND
            RELATIONSHIPS, PLANS, UNFAVORABLE, cobRDrNATION, SUSTAINABILITY,
            TRAINING, CRIT3 (IMPORTANT PROBLEM).

            4. (U) TITLE: C2: FUNCTION OF RGFR RELATIVE TO NBC TRNS AND
            VALIDATION OF RC UNITS

            5. (U) OBSERVATION: At few times could Readiness Group Fort
            Riley representatives find resources available to accomplish the
            NBC Training and Validation mission for the RC.

            6. (U) DISCUSSION: Under the Fort Riley Mob Plan, RGFR, becomes
            a Mobilization Assistance Team (MAT).

            Under the scenario conditions of Desert Shield however their MAT
            -Functions a-F training and validation did not occur because
            (presumably)-
                MAT is formed only upon partial or full mob, not for the
            200k selective caIlLtp for Desert Shield.
                ROFR Branch Assistance Teams (BAT) exist for the several
            units with pure branch affiliation making it possible +or those
            BAT to serve those units. Since few units have pure chemical
            branch affiliation, the Chemical BAT was hard pressed to assist
            all RC units in the AO.

            As a result, the burden rested first with NBC Division, Ist ID
            (M); and in November 90, -Fell to DPTM/Post Chemical (NBC
            School). With the addition of non-deployables, Post Chemical
ltaneously.
            Assistance was requested (from RG-Cml BAT) and derived to
            conduct unit inventories at HS for all alerted units to assess
            NBC equipment readiness before movement to MS.

            7. (U) LESSON LEARNED: RB-Cml BAT requires an increase of
            personnel tc) support all RC units in its AO during mobilization.

            13. (U) RECOMMENDED ACTION: Plus up the RS, Cml BAT to allow it
            to servo all RC units in its AO, especially in peacetime (to
            permit a move periodic assessment of NBC equipment readiness).

            9. (U) COMMENTS:    none



            --- (U) SUBJECT: COMMAND & CONTROL




                                       UNCLASSIFIED
                                         V-22

Document Page: First | Prev | Next | All | Image | This Release | Search


Document 5 f:/Week-27/BX001045/AFTER ACTION REPORTS PHASE I MOBILIZATION AND DEPLOYMENT/desert shield storm after action report phase 1:12269616084948
Control Fields 17
File Room = jul96_declassified
File Cabinet = Week-27
Box ID = BX001045
Unit = 1ST ID
Parent Organization = VII CORPS
Folder Title = AFTER ACTION REPORTS PHASE I MOBILIZATION AND DEPLOYMENT
Folder Seq # = 16
Subject = DESERT SHIELD STORM AFTER ACTION REPORT PHASE 1
Document Seq # = 20013
Document Date =
Scan Date =
Queued for Declassification = 01-JAN-1980
Short Term Referral = 01-JAN-1980
Long Term Referral = 01-JAN-1980
Permanent Referral = 01-JAN-1980
Non-Health Related Document = 01-JAN-1980
Declassified = 26-DEC-1996