Subject: DAILY STAFF JOURNAL LOG                                         

Box  ID: BX000002

Document Number:          2

Folder Title: DUTY LOG MAIN CP G3 20 OCT 90                                                                   

Folder Seq #:         56

Unit: XVIII CORPS 

Parent Organzation: ARCENT      











          AFZA-GT
          SUBJECT: MlAl and M2At Bradley NET


                  (7) NET crew evaluators (trainers) become the critical
          item. If there are two NET teams, each one handling a company (a
          team is 14 NCO for Abrams, 13 NCO's +or Bradleys), NET time is
          cut in hal-F--or the evaluators can get a break during the 2 month
          cycle.

                  (8) The battalion which is going through NET will run
          the ranges. Since they have experience with the weapons systems,
          there is no requirement for NET fielding team supervision. Night
          firing is a battalion commander decision and no additional
          ammunition will be provided.

                  (9) Contractor should have responsibility +or repairs of
          deficiencies found during each company's NET. Contractor
          provides the repair part (PLL will not be used during NET); the
          unit does all maintenance work. The contractor's responsibility
          ends once new vehicles are loaded on HET's +or transport to
          forward assembly areas.

              g. Post NET.

                  (1) Contractor relationship needs to be defined. During
          a regular NET, the unit works out problems for 6-8 weeks. During
          that time, the contractor pays for all parts. For MlAl's from
          POMCUS, this may not apply. For Bradleys, contractor support and
          parts should continue to come from Sultan and Faisal Ranges -For 2
          months after NET. Bradley NET contractor normally provides a
          -Field service rep with the battalion -For 6-9 months.

                  (2) We will need MCOFT. Again, the best place would
          probably be at the ranges. We can move it later.

          5. The actual schedule -For a battalion will look like:

              D-30 - Fielding conference -For battalion.
              D-20 - Hal+ DS mechanics start NET.
                   - half organizational mechanics start NET.
and test equipment issued.
                   - Battalion guards port.

              D-13 - First half organizational mechanics graduate.





                                            7

Document Page: First | Prev | Next | All | Image | This Release | Search


Document 53 f:/Week-13/BX000002/DUTY LOG MAIN CP G3 20 OCT 90/daily staff journal log:0823961435301
Control Fields 17
File Room = apr96_declassified
File Cabinet = Week-13
Box ID = BX000002
Unit = XVIII CORPS
Parent Organization = ARCENT
Folder Title = DUTY LOG MAIN CP G3 20 OCT 90
Folder Seq # = 56
Subject = DAILY STAFF JOURNAL LOG
Document Seq # = 1
Document Date =
Scan Date = 05-APR-1996
Queued for Declassification = 01-JAN-1980
Short Term Referral = 01-JAN-1980
Long Term Referral = 01-JAN-1980
Permanent Referral = 01-JAN-1980
Non-Health Related Document = 01-JAN-1980
Declassified = 23-AUG-1996